Central Plant
Project: West Campus Central Plant
General Use: Utility Plant
Status: Completed
Architect: tBP Architecture, Inc.
Contractor: DPR Construction, Inc.
Budgeted Cost: $4,124,010
Construction Start: April 2010
Opening: March 2011
Project Goal
Provide domestic, fire protection and chilled water, pressurized air and other important utilities for the Allied Health and Science Community buildings on campus.
Overview
This building will include mechanical and hydronic equipment for the Allied Health and Science Community Center buildings on campus. Other construction consists of site improvements and joint utility trenches to the Allied Health and Science Community Center buildings.
Project Status Updates
Current Bulletin: 6/18/2012
Previous Bulletin: 5/15/2012
Earlier updates have been archived. Please contact the webmaster for access.