This site has detected that you are currently browsing using Internet Explorer 8. The Yosemite Community College District website makes use of several modern web and mobile technologies that are not compatible with versions of Microsoft Internet Explorer earlier than IE 9. This incompatibility will prevent the website from displaying properly on your computer. We recommend viewing this website using a more modern web browser. This site has been tested for compatibility with all web browsers released after 2010. For assistance viewing this website, please contact the YCCD IT Service Desk at 209-575-7900

Skip to main navigation, which will allow you to navigate to a different content area. Skip to side navigation, with links to other pages from the same office you are currently viewing. Skip to the content on this page. Skip to top navigation, with office and website directories, maps, and content information. Skip to the website search box. Skip to the links at the bottom of the page, including commonly accessed links and employee resources.
 
 

Public Affairs

View Section Menu

Measure E

Bond Measure E
In November 2004, voters in the Yosemite Community College District approved Measure E, the $326 million general obligation bond for the repair, upgrade and new construction of Modesto Junior College and Columbia College facilities and the expansion of college education centers in Patterson, Oakdale, Turlock and Angels Camp.

Facilities Master Plan
In August 2002, the Yosemite Community College District Board of Trustees commissioned staff to begin the process of developing a Facilities Master Plan for the District.  Over the course of 16 months, committees representing all employee organizations and college and District personnel were established to plan the effort.  The plan was later revised in June 2004.

Bond Newsletter
The Yosemite Community College District will provide periodic updates regarding the Measure E bond program.  Measure E Updates are sent to all staff to keep the campus community current on the progress and status regarding Measure E.

Citizens' Oversight Committee
The Committee's responsibility is to oversee the use of Measure E funds and to inform the public concerning the expenditure of bond revenues.  The committee is comprised of a representative each from a college support organization, community college student, business organization, senior citizen organization, taxpayers association and at-large community representatives.

Program Management Plan
Kitchell produced the Program Management Plan (PMP) as a guidance tool for the implementation of the Measure E Bond Program.  The PMP was developed by meeting with faculty and staff for each project and validating the program requirements of each funded project in the Facilities Master Plan.  After these meetings, a resequencing occurred and was approved by the colleges to prepare the new program schedule.

The Program Management Plan reduces the program from a twelve-year program to a nine-year program.  The PMP outlines the goals, scope, budget, schedule, and program for each project.

Outreach Centers
Includes status updates on outreach center projects for the West Side Educational Center (Patterson), Calaveras Educational Center, Oakdale Educational Center and Turlock Educational Center.