Attention!

This site has detected that you are currently browsing using Internet Explorer 8. The Yosemite Community College District website makes use of several modern web and mobile technologies that are not compatible with versions of Microsoft Internet Explorer earlier than IE 9. This incompatibility will prevent the website from displaying properly on your computer. We recommend viewing this website using a more modern web browser. This site has been tested for compatibility with all web browsers released after 2010. For assistance viewing this website, please contact the YCCD IT Service Desk at 209-575-7900

Skip to main navigation, which will allow you to navigate to a different content area. Skip to side navigation, with links to other pages from the same office you are currently viewing. Skip to the content on this page. Skip to top navigation, with office and website directories, maps, and content information. Skip to the website search box. Skip to the links at the bottom of the page, including commonly accessed links and employee resources.
 
 

Measure E Bond Program

Painting West Campus

Project: Painting West Campus

General Use: Painting

Square Feet: N/A

Status: Programming

Architect: Darden Architects

Budget Cost: $2,015,000

Construction Start: TBD

Opening: TBD

Project Goal

Paint various building on the MJC West Campus.

Overview

The objective is to choose a color scheme, which will not only unify all existing buildings on campus color wise, but also give each building its own identity.

Project Status Updates

Current Bulletin: 06/04/2018

Previous Bulletin: 08/21/2017

Earlier updates have been archived. Please contact the webmaster for access.

Links of Interest

There are no links at this time.