This site has detected that you are currently browsing using Internet Explorer 8. The Yosemite Community College District website makes use of several modern web and mobile technologies that are not compatible with versions of Microsoft Internet Explorer earlier than IE 9. This incompatibility will prevent the website from displaying properly on your computer. We recommend viewing this website using a more modern web browser. This site has been tested for compatibility with all web browsers released after 2010. For assistance viewing this website, please contact the YCCD IT Service Desk at 209-575-7900
Milestone | Date Started | Date Completed | Notes |
Hardware assessment/installation of TEST environment | 4/20/15 | 4/27/15 | |
Create communication plan | 4/24/15 | 6/16/15 | Committee reviewed draft and approved final format - considered living document which can be updated as needed |
Run data scanners and clean up errors | 5/1/15 | 7/15/15 | |
Inventory all program customizations | 6/1/15 | 7/15/15 | Customizations have been inventoried and will be packaged and moved into SQL environment by Ellucian technician at the conclusion of the first DMIG |
Create test plans for all departments | 6/16/15 | 10/8/15 | Committees met on 9/25/15 to review the integration of all test plans into one roadmap to be followed during the testing phase |
First data migration into SQL TEST environment | 7/20/15 | 9/10/15 | |
Data migration cleanup | 7/27/15 | Currently working on cleanup following the completion of the first DMIG | |
Second data migration into SQL TEST environment | TBA | ||
Prepare environment for migration to PROD environment | TBA | ||
User testing | TBA | ||
Go-live preparedness | TBA | ||