Summer Semester Hours
Monday - Thursday
7:00a.m . to 5:30 p.m.
Schedule: September 8 to October 27, 2026
Area(s) Impacted: Classroom Annex, Staff Parking behind Annex
Project Summary: Addition of EV Charging stations for MJC Fleet.
Schedule:December 2026 to August 2027
Area(s) Impacted: Parking Lot 108, Home Side access (press box, bleachers, elevator, concession, entry)
Project Summary: Installation of new press box and elevator in stadium, path of travel and bleacher
improvements.
Schedule: Winter 2027
Area(s) Impacted: Poultry Unit
Project Summary: Second phase in construction of new squab building.
Schedule: July 2026 to November 2026
Area(s) Impacted: Tenaya Automotive Complex
Project Summary: Install vehicle lift for electric vehicles.
Schedule: Spring 2027
Area(s) Impacted: MJC West Campus Grounds
Project Summary: Tree trimming and maintenance services throughout campus.
Schedule: October to November 2026
Area(s) Impacted: Hillside between Toyon and Sequoia, ADA parking near site
Project Summary: Geotechnical and topographic work being done to stabilize the hillside.
Additional Information:
10-22-26 Preliminary utility location activity taking place on campus, with saw cutting of
roadway occurring. Roadway will remain open during this work, and work will be completed
by end of day.
10-23-26 Preliminary utility location activity to continue, with saw cutting in roadway, possible jack hammering and hydro excavation drilling. Roadway will remain open during the work and is expected to continue throughout the day.
10-30-26 Continued utility location activity, tree maintenance and tarping of the hillside. Roadway may be closed periodically during tree maintenance activites, but is expected to remain open most of the day.
11-13-26 Fence removal and temporary fence placement; roadway may be closed periodically during these activities, happening after business hours.
Please email facilities@yosemite.edu or desantoj@yosemite.edu with any questions.