Ag-Animal Facilities Renovation

Project Status Updates | Links of Interest

Ag Animal Facilities

Project: Ag-Animal Facilities

General Use: Agriculture

Square Feet: 15,225 Beef Unit; 5,000 Sheep Unit

Status: Bid phase for beef and sheep units is complete and contract for construction has begun.

Architect: LPAS

Contractor:  MC Dairy

Budgeted Cost: $1,500,000

Construction Start: August 2009

Opening:  March 2010

Project Goal

This project will address the existing animal facilities needs of the Beef Unit, Dairy Unit and Sheep Unit on West Campus.

Overview

This project consists of a new facility for the Beef and Dairy Programs on MJC's West Campus. It also includes a new building for the Sheep Program that includes a lambing area.

Project Status Updates

Current Bulletin: 11/11/2009

Previous Bulletin: 10/14/2009

Earlier updates have been archived. Please contact the webmaster for access.